L.D. King, Inc. was part of the team lead by DMJM/Harris (formerly Holmes and
Narver) responsible for construction management on Segments 1 through 4 of the
Route 210 freeway through Upland and Rancho Cucamonga. L.D. King, Inc. provided
the resident engineer for Segments 1 and 2, in Upland, and provided the
assistant resident engineer for Segments 3 and 4, in Upland and Rancho
Cucamonga. L.D. King, Inc. also provided five construction inspectors, working
on all four segments. The resident engineer on each of the segments was
responsible for construction contract work totaling nearly $50,000,000
Owner:
California Department of Transportation (Caltrans)
Contracting Agency:
San Bernardino Associated Governments (SanBAG)
L.D. King, Inc. provided contract
administration, field inspection, construction staking and materials
testing for the Phase 2 expansion of the East Ontario Metrolink Station,
located near Haven Avenue and Mission Boulevard.. Construction included
expansion of the existing parking lot, extensive landscaping and
irrigation improvements, signature theme structures and enhanced
concrete paving. The value of this work is approximately $2,500,000.
This project underscores the good working relationship L.D. King, Inc.
has developed with Metrolink and the Union Pacific Railroad, as it was
necessary to work closely with both of these rail agencies during the
construction of this project.